Focus on
results and change the culture along the way
How one company reduced
equipment downtime more than 50 percent in less than one
month
(Part 2 of 2)
by Robert M. Williamson
All too often, businesses try
to improve performance by "implementing"
improvement programs. Unless these programs are focused on
specific measurable and observable results, they are short
lived. Why is that? Human nature clashing with the world of
business. Getting people to quickly embrace change while
achieving sustainable business results can be challenging.
Well, here is a real
down-to-earth success story that shows how to focus on
results and change the culture along the way. The subject
plant is a very large manufacturing facility that operates
seven days, 24 hours. It is part of a multi-national
corporation producing a common product worldwide. With many
of the traditional cost-cutting, down-sizing, and ISO 9000
programs well behind them, they noticed little improvement
in their bottom line. In fact, their equipment performance
and reliability was declining at a steady pace. Something
had to be done, but the cost of doing "something"
was a real issue. They asked repeatedly, "How can we be
assured that this Total Productive Maintenance/Manufacturing
(TPM/M) approach will address the issues and give us a
significant return on our investment?" Thats the
right question. They had to see the methods and results
without taking a massive leap of faith.
The approach they took was
focused, rather than a widespread implementation. First,
they sponsored a day-long session to teach the fundamentals
of TPM/M to operations, maintenance, technical and plant
management, including about 50 salary and hourly leaders. At
the end of this session, a smaller group brainstormed
possible applications and approaches, keeping in mind
something had to be done to improve the performance and
reliability of their equipment.
Within the next few weeks,
they invited me back for a plant tour and meetings with
potential TPM/M starting points. They looked for signs of
equipment problems. They discussed equipment history and
performance data. They looked at the preventive and
predictive maintenance methods. The shops and spare parts
conditions were reviewed. Lastly, they discussed plant
process flow and the constraints or "bottlenecks."
It was unanimous. There were two major constraints, and the
most troublesome was about to get worse after January 2000
because of market demands. In fact, there were four of these
machine cells, each one identical to the others. This was to
be the TPM/M starting point. The discussion also pointed to
the next constraint to address when the first one was cured.
After some preparation, the
company assembled a "Pit Crew" to learn and apply
the elements of TPM/M to one of the four constraint machine
cells. The "Pit Crew" included a mechanic, an
electrician, a lead operator, the maintenance
coordinator/planner, the area supervisor, the reliability
leader for the department, the department process quality
technician, and the area-manufacturing manager. If the
reliability and performance of this constraint was to
improve, this was the group that had the responsibility and
the authority to do it.
Three days of "TPM/M Pit
Stop" training included a blend of classroom theory,
case studies, demonstrations, and hands-on application. The
group had full access to the equipment each afternoon during
the training. During the hands-on portions of the training,
real-time root-cause analysis was learned and performed on
all of the chronic equipment problems. With the root causes
of poor performance known, it was a matter of using the TPM/M
learnings to eliminate the causes and then establish
countermeasures to ensure they would not return. The group
then applied the proven practices and improvements to the
remaining three machine cells.
After one full month of
operation, the bottleneck no longer existed. The results to
date: 89 percent reduction in downtime-causing
contamination, more than 50 percent reduction in unplanned
machine downtime, and less operator intervention to free
jams. This new machine performance and reliability led to
increased production throughput of nearly 250 percent per
shift of operation. Additionally, work requests now have
correct machine and part nomenclature and work orders have
meaningful information on the causes of problems. Operators
have visual procedures and guides to assist in performing
their tasks. The Pit Crew continues to meet weekly to
address other machine issues and to complete the remaining
improvements. A return on the investment in TPM/M Pit Stop
training was conservatively estimated at 20 to one in less
than two months considering improved production throughput
and reduced maintenance calls!
The key learnings from this
example?
Focus on results and
change the culture along the way.
Build on the
sub-optimized systems and methods already in place.
Involve those who have
not only the responsibility but the also the authority to
make the necessary changes.
Formally train the group
using sound adult-learning principles: Adults learn by doing
and they learn what they can apply to make their work
easier.
Do things that make the
equipment easier to operate, easier to maintain, and easier
to inspect.
And most importantly,
focus on the constraints in the process the high
maintenance cost, high maintenance downtime, problem-prone
equipment equipment that if it improved would get the
attention of many people at all levels in the organization.
Oh, one last point: Not only
did they improve one of four machine cells in their plant
within a matter of a few weeks, but there are nearly 150
similar machine cells in the company, all with the same
design and chronic problems. If the company can standardize
the minor equipment improvements alone, just imagine that
return on investment!
Bob Williamson is the
president of Strategic Work Systems, a consulting firm with
offices in Greenville, S.C., and Mill Spring, N.C. For
more information, call 864-234-3100, e-mail SWS_INC@compuserve.com
or visit www.swspitcrew.com.